energyNP.com  
Tel
98510-91900 
Email
energyNP@hotmail.com 
Menu

 
 
News  
Back to energy news list >>>
 

 
 
 Air Conditioner
 Battery
 Booster Pump
 Charger
 Cold Storage Room
 Electric Power Tools
 Electric Water Heater
 Garbage Disposal
 Station
 Generator
 Heat Pump
 Inverter
 Power Supply
 Rectifiers
 Self Priming Pump
 Solar Energy
 Solar Water Heater
 Transformer
 UPS
 Voltage Stabilizer
 Wind Energy
 
  Tanahun hydropower project has been completed almost of 40%

The work of Tanahun hydropower project of 140 megawatt capacity under construction is going on in full swing here. So far, about 40 percent of the project has been completed. Rajabhai Shilpkar, the head of the project, informed that the work is being done rapidly with the aim of completing it on time and 39.42 percent of the work has been completed so far.

Under the first package, structures including a 140-meter high dam were constructed by Song Da Corporation, Vietnam-Kalika Construction Pvt. Ltd. The project is being constructed by Nepal JV. Under this, the construction of the diversion tunnel required to divert the river for the construction of the main dam has been completed. Excavation of the upper part of the dam and the slope, upgrading of the access road etc. are going on. Shilpakar said that only 500 meters of the 1,456 meters of the main tunnel that carries water is left to be drilled. According to the project, the construction of tunnels, power houses and other works are being done by Sino Hydro, China in the second package.

According to the project, the construction of 69 towers for the construction of the transmission line of Tanahun hydropower project under the third package has been completed. Shilpakar informed that the tower foundation work has reached its final stage. Shilpakar said that the compensation for the land in Tanahun and Chitwan where the tower will be placed for the construction of the transmission line has been determined and distributed. According to the project, a double circuit transmission line of 220 KV will be constructed from Damauli to Bharatpur in Chitwan. According to the project, a total of 94 towers will be constructed for the construction of transmission lines. Indian company KEC has got the job of construction of transmission line.

A total of 59 plots of 923 ropani five annas land has been acquired for the construction of transmission lines. The land belonging to Byas Municipality-13 and 14, Bandipur Rural Municipality-6, Ambukhaireni Rural Municipality-6, Devghat Rural Municipality-4 and 5 has been acquired towards Tanahun. A total of 59 plots of 923 ropani five annas land has been acquired for the construction of transmission lines. The land belonging to Byas Municipality-13 and 14, Bandipur Rural Municipality-6, Ambukhaireni Rural Municipality-6, Devghat Rural Municipality-4 and 5 has been acquired towards Tanahun. The construction of the transmission line has been set to be completed by May 2022, but there has been some delay due to the delay in obtaining permission from the Ministry of Forestry due to the epidemic of Covid-19 and tree felling in the forest area. For the first 10 years of the project’s electricity production, the annual average electricity production will be 587.7 million units, then 489.99 million units will be produced.

The overall construction of this project located in Rishing Rural Municipality-1 is targeted to be completed by June 2026. The total cost of the company’s capital structure and financial management project [including transmission line, rural electrification and interest during the construction period] for 505 million US dollars, ADB 150 million, Japan International Cooperation Agency [JICA] 184 million, European Investment Bank 80 billion 50 million and Government of Nepal. According to the project, Nepal Electricity Authority has spent 80.6 million dollars for the project.

[3 August, 2023 / nepalenergyforum.com ]   
 
 
Voltage Stabilizer Nepal Kathmandu
 
UPS Nepal Kathmandu
 
Lithium iron battery LiFePO4 Battery Nepal Kathmandu
 
Inverter Hybrid On-grid Off-Grid Energy Storage Solar Inverter Nepal Kathmandu
 
Solar Water Heater Nepal Kathmandu
 
GREE Air Conditioner Residential Nepal Kathmandu
 
Solar Water Heater Nepal Kathmandu
 
Gree Air Purifier Kills Novel Coronavirus Nepal Kathmandu
 
Battery Charger Nepal Kathmandu
 
Complete Power Solution
 
 
 
 
Solar Water Heater Nepal Kathmandu Solar Energy Nepal Kathmandu Wind Power Nepal Kathmandu Power Generator Nepal Kathmandu Voltage Stabilizer Nepal Kathmandu Transformer Nepal Kathmandu AirConditioner Nepal Kathmandu Battery Nepal Kathmandu UPS System Nepal Kathmandu Rectifier Nepal Kathmandu
 
 
Link: The Official Portal of Goverment of Nepal Nepal Electricity Authority Nepal Alternative Energy Promotion Centre Nepal Telecom Nepal Department of Agriculture Nepal Department of Industry wow Nepal! Nepal Global Buying SIMONES Industries|Nepal Power Solution
  Nepal Goverment Nepal Electricity Authority Nepal Alternative Energy Promotion Centre Nepal Telecom Nepal Department of Agriculture Nepal Department of Industry wow-Nepal | Nepal Global Buying SIMONES Industries |Nepal Power Solution
 
Fair: Investment Summit Nepal Himalayan Hydro Expo Nepal Kathmandu China International Import Expo China Import and Export Fair China-South Asia Exposition Guangzhou Int’l Refrigeration, Air-Condition, Ventilation, Air-Improving Equipment Exhibition Guangzhou International Solar Photovoltaic Exhibition Asia Battery Sourcing Fair
  Investment Summit Nepal Himalayan Hydro Expo Nepal China International Import Expo China Import and Export Fair China-South Asia Exposition Int'l Refrigeration, Air-Condition Fair Int'l Solar Photovoltaic Exhibition Asia Battery Sourcing Fair
 
Copyright @ 2014 All right reserved. Simones Industries