  Breakthrough made in 1,500-metre Tanahun Hydropower project tunnel

Photo: Amarraj Naharki/TRN Entrance of Tanahun Hydropower project tunnel.

About 1,500-metre-long tunnel of the 140-megawatt Tanahun Hydropower Project under construction in the district has been broken through.

Under Package-2, a 1,493-metre-long tunnel starting from the intake of the reservoir to the penstock pipe has been accessed through, according to the Tanahun Hydropower Project.

According to the project, the water from the main tunnel will be pumped into the underground power house through a 213-meter-long penstock pipe, and concrete lining work is underway for electricity generation.

The penstock pipe installation work has reached the final stage.

The second phase construction including the project’s tunnel, powerhouse construction and import, supply and installation and operation of hydromechanics and electromechanical equipment is being done by the Sino Hydro, China.

The construction of the civil structure of the powerhouse is also in the final stage, said project chief Shyamji Bhandari. According to Bhandari, the construction of the switchyard and installation of equipment in the powerhouse are underway.

The overall physical progress of this package is about 62 per cent.

Under Package-3, KEC International Limited, India is constructing a 220 kV double-circuit transmission line from Damauli to Bharatpur in Chitwan.

Out of the 94 towers on the 34.7 km transmission line, the foundation of 78 towers has been laid and 69 towers have been erected.

The overall construction progress of the package is 74 per cent.

Recently, a high-level team of the Asian Development Bank (ADB) and the Nepal Electricity Authority inspected the project under construction on the Seti River in Tanahun.

The overall progress of the project under construction, which has been divided into three packages, is 63 per cent.

The construction of the projects is targeted to be completed by May 2026, said Kiran Kumar Shrestha, Managing Director of the project.

A 140-meter-high main dam is being constructed on the Seti River, which flows through the border of Rishing Rural Municipality-1 and Byas Municipality-5.

The construction progress of Package-1 is about 36 per cent. The construction of Package-1 is being done by Song Da Corporation, Vietnam-Kalika Construction Private Limited and Nepal JV. The total cost of the project is 505 million US dollars.

Of that, Asian Development Bank will bear US$ 150 million, Japan International Cooperation Agency (JICA) US$ 184 million, European Investment Bank US$ 85 million and the Government of Nepal/Nepal Electricity Authority US$ 86.

[ 17 December, 2024 / risingnepaldaily.com ]   
 
 
Voltage Stabilizer Nepal Kathmandu
 
UPS Nepal Kathmandu
 
Lithium iron battery LiFePO4 Battery Nepal Kathmandu
 
Inverter Hybrid On-grid Off-Grid Energy Storage Solar Inverter Nepal Kathmandu
 
Solar Water Heater Nepal Kathmandu
 
GREE Air Conditioner Residential Nepal Kathmandu
 
Solar Water Heater Nepal Kathmandu
 
Gree Air Purifier Kills Novel Coronavirus Nepal Kathmandu
 
Battery Charger Nepal Kathmandu
 
Complete Power Solution
 
 
 
 
Solar Water Heater Nepal Kathmandu Solar Energy Nepal Kathmandu Wind Power Nepal Kathmandu Power Generator Nepal Kathmandu Voltage Stabilizer Nepal Kathmandu Transformer Nepal Kathmandu AirConditioner Nepal Kathmandu Battery Nepal Kathmandu UPS System Nepal Kathmandu Rectifier Nepal Kathmandu
 
 
Link: The Official Portal of Goverment of Nepal Nepal Electricity Authority Nepal Alternative Energy Promotion Centre Nepal Telecom Nepal Department of Agriculture Nepal Department of Industry wow Nepal! Nepal Global Buying SIMONES Industries|Nepal Power Solution
  Nepal Goverment Nepal Electricity Authority Nepal Alternative Energy Promotion Centre Nepal Telecom Nepal Department of Agriculture Nepal Department of Industry wow-Nepal | Nepal Global Buying SIMONES Industries |Nepal Power Solution
 
Fair: Investment Summit Nepal Himalayan Hydro Expo Nepal Kathmandu China International Import Expo China Import and Export Fair China-South Asia Exposition Guangzhou Int’l Refrigeration, Air-Condition, Ventilation, Air-Improving Equipment Exhibition Guangzhou International Solar Photovoltaic Exhibition Asia Battery Sourcing Fair
  Investment Summit Nepal Himalayan Hydro Expo Nepal China International Import Expo China Import and Export Fair China-South Asia Exposition Int'l Refrigeration, Air-Condition Fair Int'l Solar Photovoltaic Exhibition Asia Battery Sourcing Fair
 
Copyright @ 2014 All right reserved. Simones Industries