energyNP.com  
Tel
98510-91900 
Email

Er.energyNP@Gmail.com

        energyNP@hotmail.com
Menu

 
 
News  
Back to energy news list >>>
 

 
 
 Air Conditioner
 Battery
 Booster Pump
 Charger
 Cold Storage Room
 Electric Power Tools
 Electric Water Heater
 Garbage Disposal
 Station
 Generator
 Heat Pump
 Inverter
 Lead Acid Battery
 LiFePO4 Battery
 Power Supply
 Rectifiers
 Self Priming Pump
 Solar Energy
 Solar Water Heater
 Transformer
 Treadmill
 UPS
 Voltage Stabilizer
 Wind Energy

 
Portable Electric Car Charger | Portable EV Charger | Portable Charger for Home Use | Charging Station for Home Use | Kathmandu Nepal
 
Electric Folded Treadmill Nepal Kathmandu
 
Gree Air Conditioner Nepal Kathmandu
 
Solar Water Heater Nepal Kathmandu
 
Solar Water Heater Nepal Kathmandu
 
Gree Air Purifier Kills Novel Coronavirus Nepal Kathmandu
 

 

 
  Madhesh Accelerates Strategic Power Projects to Meet Rising Industrial Demand

The government has accelerated the construction of transmission lines and substations in Madhesh Province to address growing electricity demand, weak distribution infrastructure, and supply challenges in the industrial sector.

The Ministry of Energy, Water Resources and Irrigation has moved ahead with the expansion of strategic transmission infrastructure in Madhesh to meet both current electricity demand and the additional demand expected from industries, businesses, and household consumers in the coming years.

The completion of new transmission lines and substations is expected to improve electricity quality and supply reliability in Madhesh Province while providing the energy infrastructure needed for industrial expansion. The ministry has been conducting regular monitoring, coordination, and facilitation to ensure that projects under construction are completed on schedule.

Energy, Water Resources and Irrigation Minister Biraj Bhakta Shrestha said transmission line and substation projects aimed at addressing electricity demand in Madhesh Province have reached important stages of construction.

According to him, around 24 kilometers of the double-circuit 132 kV transmission line under the Dhalkebar-Balganga 132 kV Transmission Line and Substation Project has already been successfully charged under no-load conditions. Construction and equipment installation works at the Balganga Substation are also progressing rapidly.

Minister Shrestha said work is underway with the target of bringing the project into operation before Dashain. Once operational, the project is expected to strengthen the distribution system in Mujelia, Yadukaha, Dhanushadham, Birendra Bazaar, Lohana and Nagarain, as well as across Dhanusha district.

The estimated cost of the Dhalkebar-Balganga 132 kV Transmission Line and Substation Project is around Rs 2.136 billion. The project includes approximately 24 kilometers of double-circuit 132 kV transmission line and a 63 MVA, 132/33 kV substation in Hansapur Municipality-9.

The transmission line, which will originate from Tower No. 30 of the Dhalkebar-Loharpatti 132 kV line, will be connected to the Balganga Substation. The transmission line was charged under no-load conditions in July. Most of the major equipment and the power transformer for the Balganga Substation have already arrived at the project site. Civil construction has reached its final stage, while equipment installation is underway. Construction of the control room and staff residential building is also nearing completion.

Infrastructure to Meet Growing East-West Electricity Demand

The growing load on 33 kV and 11 kV distribution lines has emerged as a major challenge for Madhesh Province’s electricity system. In particular, rising electricity demand in rural and industrial areas of Siraha and Saptari is putting pressure on the existing distribution infrastructure, making it difficult to accommodate future demand.

To address this issue, the Lahan-Sukhipur 132 kV Transmission Line Project has been initiated. Around 17 kilometers of double-circuit transmission line will be constructed from the existing Lahan Substation to the proposed 132/33/11 kV substation at Sukhipur.

The Sukhipur Substation will have two 63 MVA transformers and one 24 MVA transformer. Two 132 kV line bays will also be added at the Lahan Substation.

The project has an estimated cost of around Rs 1.53 billion. Its feasibility and environmental studies have already been completed. The boundary wall of the Sukhipur Substation has been constructed, and the construction permit has also been obtained.

Land acquisition required for construction of the transmission line towers is in its final stage. The contractor has already started work with a target of completing, testing, and commissioning the transmission line within 24 months. The remaining land acquisition is targeted for completion by Bhadra.

Transmission Infrastructure Expansion in Saptari

The Rupani-Bodebarsain 132 kV Transmission Line Project has been advanced in Saptari in view of growing electricity demand and the district’s industrial potential.

According to the Nepal Electricity Authority (NEA), preparations are underway to construct around 18 kilometers of double-circuit transmission line and establish a new 132/33/11 kV substation at Bodebarsain.

The proposed substation will have two 30 MVA transformers and one 24 MVA transformer. Two 132 kV line bays will be added at the Rupani Substation.

The project is expected to improve electricity supply in central and southeastern areas of Saptari and facilitate the integration of additional power generation into the system in the future.

The estimated cost of the project is around Rs 1.56 billion. Studies have been completed, while construction of the substation boundary wall and acquisition of the construction permit have also been completed. The cost estimate for the transmission line has been approved, and the process of preparing tender documents has begun, according to the NEA.

Improvements in Central and Southern Rautahat

In Rautahat, work is underway to increase transmission capacity in the central and southern areas through the Chandrapur-Sukhdev Chowk 132 kV Transmission Line Project.

Around 37 kilometers of double-circuit transmission line will be constructed from the existing substation at Chandranigahapur to the proposed substation at Saruatha in Yamunamai Rural Municipality-4.

A 132/33/11 kV substation will be constructed at Saruatha, with plans to install two 63 MVA, 132/33 kV transformers and two 24 MVA, 33/11 kV transformers.

The transmission line will help provide more reliable electricity supply to distribution centers serving Gaur, Manpur, Simraungadh and Maulapur.

Around seven kilometers of the transmission line will pass through national forest areas, so approval for the forest area and land acquisition for the towers are underway. Most pre-construction activities, including detailed feasibility and environmental studies, land acquisition for the substation, and construction of the boundary wall and security building, have already been completed.

The check survey, tower profiling, pegging, pit marking and cadastral mapping work for the transmission line has also been completed.

A construction agreement for the Chandrapur-Saruatha transmission line was signed with the contractor in July. The project has a contract value of around Rs 938.24 million and a construction period of 30 months. The procurement process for the Saruatha Substation is also underway.

High-Capacity Transmission Line for Bara-Parsa Industrial Areas

As electricity demand continues to rise rapidly in the Bara-Parsa area, which has developed as an industrial corridor, the Hetauda-Parwanipur-Pokhariya 132 kV Transmission Line Project has also been advanced as an important infrastructure project.

The major components of the project include construction of a 21.21-kilometer, 132 kV four-circuit transmission line from Parwanipur to Pokhariya, construction of a new 132/33/11 kV substation at Pokhariya, and bay expansion at the Parwanipur Substation.

Earlier, reconductoring of the 17-kilometer 132 kV double-circuit Piluwa (Pathlaiya)-Parwanipur line using high-temperature low-sag conductors had already been completed.

At the Pokhariya Substation, construction of the control room, staff quarters, store, guard house, and foundations for equipment and transformers is underway. The design of the four-circuit towers has been approved, while the revised Initial Environmental Examination has also been approved.

The tendering process has been completed and a construction agreement has been signed with a Chinese company. The NEA said the project is targeted for completion by September 2027.

Once these transmission lines and substations are completed, the electricity supply infrastructure in Madhesh Province is expected to become significantly stronger. The projects will particularly help manage rising electricity demand in Dhanusha, Siraha, Saptari, Rautahat and the industrial areas of Bara-Parsa.

The government has emphasized developing transmission infrastructure capable of meeting future demand rather than waiting for demand to rise before expanding infrastructure. This is expected to support the development of energy infrastructure required for greater industrial investment, increased production and job creation.

Nepalpurbadhar

[ 12 Aug 2026 / nepalenergyforum.com ]   
 

Infrared Cooktop | Infrared Cooker | Infra red Cooking Range | Electric Cooktop | Electric Cooker | Nepal | Kathmandu | Induction Cooktop | Induction cooker | energyNP.com | Pottery Furnace Dual Infrared Cooker Double Panels Infrared Cooktop Inteligent Touch Electric Ceramic

 SYSTEM
 Backup System
 Solar System
 Wind Power System
 Heating System

 AC & Ventilation
 System

 Cold Room System
 Charging System
 for
 Telecom/Industry
 Substation System

 
Voltage Stabilizer Nepal Kathmandu
 
UPS Nepal Kathmandu
 
Lithium iron battery Battery Nepal Kathmandu
 
Inverter Hybrid On-grid Off-Grid Energy Storage Solar Inverter Nepal Kathmandu
 
Solar Energy - Nepal Kathmandu
 
Complete Power Solution
 
 
 
 
Solar Water Heater Nepal Kathmandu Solar Energy Nepal Kathmandu Wind Power Nepal Kathmandu Power Generator Nepal Kathmandu Voltage Stabilizer Nepal Kathmandu Transformer Nepal Kathmandu AirConditioner Nepal Kathmandu Battery Nepal Kathmandu UPS System Nepal Kathmandu Rectifier Nepal Kathmandu
 
 
Link: The Official Portal of Goverment of Nepal Nepal Electricity Authority Nepal Alternative Energy Promotion Centre Nepal Telecom Nepal Department of Agriculture Nepal Department of Industry wow Nepal! Nepal Global Buying SIMONES Industries|Nepal Power Solution
  Nepal Goverment Nepal Electricity Authority Nepal Alternative Energy Promotion Centre Nepal Telecom Nepal Department of Agriculture Nepal Department of Industry wow-Nepal | Nepal Global Buying SIMONES Industries |Nepal Power Solution
 
Fair: Investment Summit Nepal Himalayan Hydro Expo Nepal Kathmandu China International Import Expo China Import and Export Fair China-South Asia Exposition Guangzhou Int’l Refrigeration, Air-Condition, Ventilation, Air-Improving Equipment Exhibition Guangzhou International Solar Photovoltaic Exhibition Asia Battery Sourcing Fair
  Investment Summit Nepal Himalayan Hydro Expo Nepal China International Import Expo China Import and Export Fair China-South Asia Exposition Int'l Refrigeration, Air-Condition Fair Int'l Solar Photovoltaic Exhibition Asia Battery Sourcing Fair
 
Copyright @ 2014 All right reserved. Simones Industries