energyNP.com  
Tel
98510-91900 
Email

Er.energyNP@Gmail.com

        energyNP@hotmail.com
Menu

 
 
News  
Back to energy news list >>>
 

 
 
 Air Conditioner
 Battery
 Booster Pump
 Charger
 Cold Storage Room
 Electric Power Tools
 Electric Water Heater
 Garbage Disposal
 Station
 Generator
 Heat Pump
 Inverter
 Lead Acid Battery
 LiFePO4 Battery
 Power Supply
 Rectifiers
 Self Priming Pump
 Solar Energy
 Solar Water Heater
 Transformer
 Treadmill
 UPS
 Voltage Stabilizer
 Wind Energy

 
Portable Electric Car Charger | Portable EV Charger | Portable Charger for Home Use | Charging Station for Home Use | Kathmandu Nepal
 
Electric Folded Treadmill Nepal Kathmandu
 
Gree Air Conditioner Nepal Kathmandu
 
Solar Water Heater Nepal Kathmandu
 
Solar Water Heater Nepal Kathmandu
 
Gree Air Purifier Kills Novel Coronavirus Nepal Kathmandu
 

 

 
  Tanahun Hydropower Project Construction Accelerates, Overall Progress Reaches 77.5 Percent

Construction of the 140 MW Tanahun Hydropower Project, a national-priority reservoir project being developed under the full ownership of Nepal Electricity Authority (NEA), has gathered momentum, with overall physical progress reaching 77.5 percent.

The project, being constructed on the Seti River with concessional financing from the Government of Nepal, NEA and international development partners including the Asian Development Bank (ADB), Japan International Cooperation Agency (JICA) and the European Investment Bank (EIB), has divided its major construction works into three packages.

The project is regarded as strategically important for strengthening Nepal’s energy security and expanding the country’s experience in developing reservoir-based hydropower projects.

Main dam construction reaches 62 percent

Under the first package, construction of the 140-metre-high main dam and associated structures is being carried out by Sinohydro-Kalika JV.

The Seti River diversion and construction of the cofferdam at the dam site have already been completed. Concrete placement for the main dam began in March/Chaitra 2025, and approximately 448,516 cubic metres of concrete has been placed so far.

The overall physical progress of Package I has reached 62 percent.

The dam is one of the most critical components of the project, as the reservoir created by the structure will enable regulated water flow and support electricity generation throughout the year.

Underground powerhouse and electromechanical works advance

Construction under Package II is being carried out by Sinohydro Corporation. Major civil works related to the underground powerhouse, main tunnel, cable tunnel and surge tank have already been completed.

The overall progress of the second package has reached 78.5 percent.

With major excavation and civil works substantially completed, the project has entered a crucial phase involving the installation of electromechanical equipment. Turbines, generators, main inlet valves, transformers and other equipment are being installed.

The main access tunnel, audit tunnels, main tunnel and the 46.88-metre-high intake shaft with a diameter of 14.3 metres have been excavated completely.

Concrete works for the powerhouse, cable tunnel and tailrace structures have also been completed, while installation of turbine, generator and transformer equipment is continuing.

Tanahun Hydropower Limited Project Manager Shyamji Bhandari said construction was progressing according to schedule.

“We are working according to the timeline, and more than 77 percent of the project has already been completed,” Bhandari said. He added that work on the hydromechanical components, transmission line and dam was progressing rapidly.

According to him, completion of the project will strengthen Nepal’s energy security while also increasing confidence in the development of additional reservoir-based hydropower projects in the country.

220 kV transmission line reaches 81 percent

Construction of the 35-kilometre, 220 kV transmission line from Damauli to Bharatpur, being developed under Package III, has also reached its final stage.

The package is being implemented by India-based KEC International, with overall progress reaching 81 percent.

Of the total 94 transmission towers, foundation works for 82 towers have been completed, while 72 towers have already been erected.

Tree cutting and safe storage within community forests along the transmission line right-of-way in Tanahun and Chitwan are being carried out in accordance with prescribed health, safety and environmental standards.

Orientation programmes on tree cutting and safe storage have also been conducted in the affected community forests before the work was undertaken.

Community and environmental programmes continue

Alongside the physical construction, the project has continued social and environmental safeguard programmes in affected areas.

Under community development programmes implemented through local consumer committees, dozens of projects have already been completed, including access roads, bridges and school buildings. The project management says several additional schemes are currently under implementation.

In the affected areas, consultations are also continuing with local residents on land acquisition in the buffer zone, verification of claims over ailani (unregistered) land and compensation determination.

The compensation determination process has been accelerated, including collection of claims relating to ailani land in the dam inundation and buffer-zone areas and field verification by surveying technicians.

As part of the Gender Equality and Social Inclusion programme, women from the Magar community in Paltyang of Rishing Rural Municipality-8 have been supported through off-season vegetable farming and financial literacy training. Agricultural equipment and hand tractors have also been distributed under the programme.

Orientation on safeguard policies has additionally been provided to officials of the compensation determination committee to make land acquisition and compensation distribution more transparent.

ADB delegation reviews project progress

An ADB delegation led by an alternate member of the ADB Board of Directors visited the project site in July 2026 to review the overall progress and implementation of environmental and social safeguard policies.

Following the field visit, the delegation reportedly assessed the project’s progress as satisfactory.

Lower Seti project being advanced

The Tanahun project is also expected to create an opportunity for further hydropower development downstream.

A 126 MW Lower Seti Hydropower Project is being advanced in the downstream area by utilizing the regulated flow from the Tanahun project.

The detailed project report (DPR) for Lower Seti has been prepared, while its Environmental Impact Assessment (EIA) report has been submitted to the Ministry of Forests and Environment for approval. Work on an exploratory tunnel is also underway.

The development of the Lower Seti project is expected to enable further utilization of the regulated water flow generated by the Tanahun reservoir.

Project cost exceeds $500 million

The total estimated cost of the Tanahun Hydropower Project stands at approximately US$505 million, including the transmission line, rural electrification and interest during the construction period.

Of the total financing, ADB is providing US$150 million, JICA US$184 million, EIB US$85 million, while the Government of Nepal and Nepal Electricity Authority are contributing US$87 million.

Loan agreements between the Government of Nepal and the respective development partners, as well as subsidiary loan agreements between the Government and NEA and between NEA and Tanahun Hydropower Limited, have already been concluded.

With the dam, underground powerhouse, electromechanical installations and transmission infrastructure moving ahead simultaneously, the project is now entering a decisive stage of construction.

The authorities are aiming to complete the project within the stipulated timeframe, with the 140 MW reservoir-based plant expected to make a significant contribution to Nepal’s domestic electricity supply, energy security and long-term hydropower development.

[ 19 Aug 2026 / fiscalnepal.com ]   
 

Infrared Cooktop | Infrared Cooker | Infra red Cooking Range | Electric Cooktop | Electric Cooker | Nepal | Kathmandu | Induction Cooktop | Induction cooker | energyNP.com | Pottery Furnace Dual Infrared Cooker Double Panels Infrared Cooktop Inteligent Touch Electric Ceramic

 SYSTEM
 Backup System
 Solar System
 Wind Power System
 Heating System

 AC & Ventilation
 System

 Cold Room System
 Charging System
 for
 Telecom/Industry
 Substation System

 
Voltage Stabilizer Nepal Kathmandu
 
UPS Nepal Kathmandu
 
Lithium iron battery Battery Nepal Kathmandu
 
Inverter Hybrid On-grid Off-Grid Energy Storage Solar Inverter Nepal Kathmandu
 
Solar Energy - Nepal Kathmandu
 
Complete Power Solution
 
 
 
 
Solar Water Heater Nepal Kathmandu Solar Energy Nepal Kathmandu Wind Power Nepal Kathmandu Power Generator Nepal Kathmandu Voltage Stabilizer Nepal Kathmandu Transformer Nepal Kathmandu AirConditioner Nepal Kathmandu Battery Nepal Kathmandu UPS System Nepal Kathmandu Rectifier Nepal Kathmandu
 
 
Link: The Official Portal of Goverment of Nepal Nepal Electricity Authority Nepal Alternative Energy Promotion Centre Nepal Telecom Nepal Department of Agriculture Nepal Department of Industry wow Nepal! Nepal Global Buying SIMONES Industries|Nepal Power Solution
  Nepal Goverment Nepal Electricity Authority Nepal Alternative Energy Promotion Centre Nepal Telecom Nepal Department of Agriculture Nepal Department of Industry wow-Nepal | Nepal Global Buying SIMONES Industries |Nepal Power Solution
 
Fair: Investment Summit Nepal Himalayan Hydro Expo Nepal Kathmandu China International Import Expo China Import and Export Fair China-South Asia Exposition Guangzhou Int’l Refrigeration, Air-Condition, Ventilation, Air-Improving Equipment Exhibition Guangzhou International Solar Photovoltaic Exhibition Asia Battery Sourcing Fair
  Investment Summit Nepal Himalayan Hydro Expo Nepal China International Import Expo China Import and Export Fair China-South Asia Exposition Int'l Refrigeration, Air-Condition Fair Int'l Solar Photovoltaic Exhibition Asia Battery Sourcing Fair
 
Copyright @ 2014 All right reserved. Simones Industries