energyNP.com  
Tel
98510-91900 
Email

Er.energyNP@Gmail.com

        energyNP@hotmail.com
Menu

 
 
News  
Back to energy news list >>>
 

 
 
 Air Conditioner
 Battery
 Booster Pump
 Charger
 Cold Storage Room
 Electric Power Tools
 Electric Water Heater
 Garbage Disposal
 Station
 Generator
 Heat Pump
 Inverter
 Lead Acid Battery
 LiFePO4 Battery
 Power Supply
 Rectifiers
 Self Priming Pump
 Solar Energy
 Solar Water Heater
 Transformer
 Treadmill
 UPS
 Voltage Stabilizer
 Wind Energy

 
Portable Electric Car Charger | Portable EV Charger | Portable Charger for Home Use | Charging Station for Home Use | Kathmandu Nepal
 
Electric Folded Treadmill Nepal Kathmandu
 
Gree Air Conditioner Nepal Kathmandu
 
Solar Water Heater Nepal Kathmandu
 
Solar Water Heater Nepal Kathmandu
 
Gree Air Purifier Kills Novel Coronavirus Nepal Kathmandu
 

 

 
  NEA Introduces Four-Group RCOD Framework, Extends Deadline for Eligible Hydropower Projects

Kathmandu. The deadline for hydropower projects that have signed Power Purchase Agreements (PPAs) and reached various stages of construction but could not come into operation within the stipulated time will be extended. The Nepal Electricity Authority has put forward a new action plan to address the demand for extension of the RCOD (Commercial Production Start Date) deadline, which has been raised by energy producers for a long time.

The Authority stated that the meeting of the Authority’s board of directors held on 16th July decided to classify the projects into four groups based on their physical progress, implementation of PPA obligations, and current status.

NEA’s acting Managing director Dirghayu Shrestha informed that the process of extending the deadline for the commercial production start date, or RCOD, of hydropower projects is proceeding regularly.

He said that the deadline extension work is being done by creating a procedure to give equal opportunity to all promoters.

According to him, the authority to extend the deadline as per the PPA provision rests with the executive director. ‘The deadline for 8-10 projects that have been stalled for a long time has been extended,’ he said.

Shrestha said that only in cases where a lump-sum extension of the deadline is required due to force majeure events like COVID-19, it needs to be presented to the Authority’s board of directors, while extensions for other normal circumstances are being processed at the MD level.

Classification of Projects into Four Groups

Group A: Projects with Satisfactory Progress

Group A includes projects whose RCOD deadline has not expired. They are placed in this category if they have fulfilled PPA conditions such as production license, financial management, and land management on time or are in a position to fulfill them within the stipulated time.

Group B: Projects Delayed Due to Authority or Unforeseen Circumstances

Projects whose RCOD has expired but could not come into operation due to reasons attributable to the Authority (non-construction of transmission lines or substations) fall into this group.

Projects confirmed to have faced unforeseen circumstances and achieved more than 25 percent physical progress within the RCOD period are also placed in this group. These projects will be strictly monitored by the Electricity Trading Department, and instructions will be given to move forward with the work.

Group C: Projects with Weak Progress

Projects whose RCOD has not expired but have not fulfilled key obligations (financial management, land acquisition, etc.) or have less than 25 percent physical progress by the RCOD expiry date fall into this category.

A Notice of Default will be issued to such projects, and if a satisfactory response is not received, the process of contract cancellation will be initiated, the Authority has stated.

Group D: Projects with Cancelled Licenses or Abandoned Projects

Projects that have not fulfilled any legal or physical obligations even after the RCOD has expired, and whose survey or production licenses have been cancelled, are placed in this group.

How is Physical Progress Measured?

The Authority has set clear criteria for measuring physical progress. In the case of hydropower, the construction of main structures such as headworks, tunnels, pipe alignments, and powerhouses will be considered. In the case of solar projects, panel purchase agreements, LC, land management, and the commencement of foundation construction will be considered indicators of progress. The calculation of 25 percent progress will be in accordance with the Physical Progress Related Work Procedure 2071.

Goal to Make it Organized and Transparent

This decision by the Authority is believed to encourage promoters who are genuinely working and discourage those who are holding onto projects without working on them. A provision has also been made to reclassify projects in Group B after regular monitoring for up to six months, as needed.

The Authority expects that this arrangement will help make electricity project management more organized, transparent, and accountable, as well as facilitate the faster connection of electricity to the national grid.

Projects whose RCOD period has expired but have not fulfilled obligations mentioned in the PPA, such as obtaining a production license, financial management, land management, or whose survey and production licenses have been cancelled, will be included.

Physical progress measurement will be in accordance with the work procedure determined by the Nepal Electricity Authority. The commencement of construction of main structures (such as headworks, pipe alignments, tunnels, powerhouses, etc.) and the achievement of progress will be considered the basis for physical progress.

Similarly, projects falling under Group C will be issued a Notice of Default as per the PPA provisions. If a satisfactory response is not received or no improvement is observed, the process of contract cancellation will also be initiated.

This is expected to create a clear distinction between projects that have been stalled for a long time, projects that are progressing, and projects that have been delayed in coming into operation, thereby making electricity project management more organized, transparent, and accountable.

Ratopati

[ 20 Jul 2026 / nepalenergyforum.com ]   
 

Infrared Cooktop | Infrared Cooker | Infra red Cooking Range | Electric Cooktop | Electric Cooker | Nepal | Kathmandu | Induction Cooktop | Induction cooker | energyNP.com | Pottery Furnace Dual Infrared Cooker Double Panels Infrared Cooktop Inteligent Touch Electric Ceramic

 SYSTEM
 Backup System
 Solar System
 Wind Power System
 Heating System

 AC & Ventilation
 System

 Cold Room System
 Charging System
 for
 Telecom/Industry
 Substation System

 
Voltage Stabilizer Nepal Kathmandu
 
UPS Nepal Kathmandu
 
Lithium iron battery Battery Nepal Kathmandu
 
Inverter Hybrid On-grid Off-Grid Energy Storage Solar Inverter Nepal Kathmandu
 
Solar Energy - Nepal Kathmandu
 
Complete Power Solution
 
 
 
 
Solar Water Heater Nepal Kathmandu Solar Energy Nepal Kathmandu Wind Power Nepal Kathmandu Power Generator Nepal Kathmandu Voltage Stabilizer Nepal Kathmandu Transformer Nepal Kathmandu AirConditioner Nepal Kathmandu Battery Nepal Kathmandu UPS System Nepal Kathmandu Rectifier Nepal Kathmandu
 
 
Link: The Official Portal of Goverment of Nepal Nepal Electricity Authority Nepal Alternative Energy Promotion Centre Nepal Telecom Nepal Department of Agriculture Nepal Department of Industry wow Nepal! Nepal Global Buying SIMONES Industries|Nepal Power Solution
  Nepal Goverment Nepal Electricity Authority Nepal Alternative Energy Promotion Centre Nepal Telecom Nepal Department of Agriculture Nepal Department of Industry wow-Nepal | Nepal Global Buying SIMONES Industries |Nepal Power Solution
 
Fair: Investment Summit Nepal Himalayan Hydro Expo Nepal Kathmandu China International Import Expo China Import and Export Fair China-South Asia Exposition Guangzhou Int’l Refrigeration, Air-Condition, Ventilation, Air-Improving Equipment Exhibition Guangzhou International Solar Photovoltaic Exhibition Asia Battery Sourcing Fair
  Investment Summit Nepal Himalayan Hydro Expo Nepal China International Import Expo China Import and Export Fair China-South Asia Exposition Int'l Refrigeration, Air-Condition Fair Int'l Solar Photovoltaic Exhibition Asia Battery Sourcing Fair
 
Copyright @ 2014 All right reserved. Simones Industries