energyNP.com  
Tel
98510-91900 
Email

Er.energyNP@Gmail.com

        energyNP@hotmail.com
Menu

 
 
News  
Back to energy news list >>>
 

 
 
 Air Conditioner
 Battery
 Booster Pump
 Charger
 Cold Storage Room
 Electric Power Tools
 Electric Water Heater
 Garbage Disposal
 Station
 Generator
 Heat Pump
 Inverter
 Lead Acid Battery
 LiFePO4 Battery
 Power Supply
 Rectifiers
 Self Priming Pump
 Solar Energy
 Solar Water Heater
 Transformer
 Treadmill
 UPS
 Voltage Stabilizer
 Wind Energy

 
Portable Electric Car Charger | Portable EV Charger | Portable Charger for Home Use | Charging Station for Home Use | Kathmandu Nepal
 
Electric Folded Treadmill Nepal Kathmandu
 
Gree Air Conditioner Nepal Kathmandu
 
Solar Water Heater Nepal Kathmandu
 
Solar Water Heater Nepal Kathmandu
 
Gree Air Purifier Kills Novel Coronavirus Nepal Kathmandu
 

 

 
  Tanahu Hydropower Project’s Main Dam Construction Reaches 62% Completion

Construction of the main dam of the 140-megawatt Tanahu Hydropower Project, under construction in Rishing Rural Municipality of Tanahu, has gained momentum. So far, 62 percent of the work on the 140-meter-high main dam being constructed under Package 1 of the project has been completed.

Project Chief Shyamji Bhandari said a total of 850,000 cubic meters of concrete is required for construction of the main dam, of which 473,761 cubic meters has been placed so far.

According to him, the main dam is one of the project’s key structures. As concrete placement work at the dam is continuing, construction progress is expected to accelerate further in the coming days.

Song Da-Kalika JV has been contracted to construct the dam and other structures under Package 1. Project Chief Bhandari said the overall physical progress of the package has reached 59 percent.

Under Package 1, excavation of the hill required for construction of the main dam, construction of access roads, construction of a temporary dam to divert the Seti River, and construction of two diversion tunnels have already been completed. The flow of the Seti River has also been diverted for construction of the main dam.

Temporary dams have been completed both upstream and downstream of the main dam. Likewise, all eight grouting tunnels located on both sides of the dam have been constructed. Concrete placement for the main dam began on March 20, 2025.

To strengthen and stabilize the dam foundation, core drilling, water pressure testing, consolidation grouting, and curtain grouting have been completed in various grouting galleries.

Similarly, shotcrete application, installation of wire mesh, and construction of gabions for slope stabilization around the dam and river protection are also continuing. According to the project, work on structures related to the dam is progressing in line with the scheduled targets.

Construction of the Tanahu Hydropower Project is being carried out under three packages. Package 1 covers construction of the main dam and associated structures.

Jalasarokar

[ 19 Aug 2026 / nepalenergyforum.com ]   
 

Infrared Cooktop | Infrared Cooker | Infra red Cooking Range | Electric Cooktop | Electric Cooker | Nepal | Kathmandu | Induction Cooktop | Induction cooker | energyNP.com | Pottery Furnace Dual Infrared Cooker Double Panels Infrared Cooktop Inteligent Touch Electric Ceramic

 SYSTEM
 Backup System
 Solar System
 Wind Power System
 Heating System

 AC & Ventilation
 System

 Cold Room System
 Charging System
 for
 Telecom/Industry
 Substation System

 
Voltage Stabilizer Nepal Kathmandu
 
UPS Nepal Kathmandu
 
Lithium iron battery Battery Nepal Kathmandu
 
Inverter Hybrid On-grid Off-Grid Energy Storage Solar Inverter Nepal Kathmandu
 
Solar Energy - Nepal Kathmandu
 
Complete Power Solution
 
 
 
 
Solar Water Heater Nepal Kathmandu Solar Energy Nepal Kathmandu Wind Power Nepal Kathmandu Power Generator Nepal Kathmandu Voltage Stabilizer Nepal Kathmandu Transformer Nepal Kathmandu AirConditioner Nepal Kathmandu Battery Nepal Kathmandu UPS System Nepal Kathmandu Rectifier Nepal Kathmandu
 
 
Link: The Official Portal of Goverment of Nepal Nepal Electricity Authority Nepal Alternative Energy Promotion Centre Nepal Telecom Nepal Department of Agriculture Nepal Department of Industry wow Nepal! Nepal Global Buying SIMONES Industries|Nepal Power Solution
  Nepal Goverment Nepal Electricity Authority Nepal Alternative Energy Promotion Centre Nepal Telecom Nepal Department of Agriculture Nepal Department of Industry wow-Nepal | Nepal Global Buying SIMONES Industries |Nepal Power Solution
 
Fair: Investment Summit Nepal Himalayan Hydro Expo Nepal Kathmandu China International Import Expo China Import and Export Fair China-South Asia Exposition Guangzhou Int’l Refrigeration, Air-Condition, Ventilation, Air-Improving Equipment Exhibition Guangzhou International Solar Photovoltaic Exhibition Asia Battery Sourcing Fair
  Investment Summit Nepal Himalayan Hydro Expo Nepal China International Import Expo China Import and Export Fair China-South Asia Exposition Int'l Refrigeration, Air-Condition Fair Int'l Solar Photovoltaic Exhibition Asia Battery Sourcing Fair
 
Copyright @ 2014 All right reserved. Simones Industries